Project Summary
The project comprised of major Structural alterations to the internal fabric of the property, including the formation of a new single-story basement under 60% of the dwelling.
This was a particularly challenging project which involved a comprehensive temporary works design to allow the basement and upper floor works to progress simultaneously, in order to reduce the overall programme duration.
Our site team worked closely with both the permanent and temporary works engineers, to ensure a safe and efficient construction environment was in place throughout all phases of the structural works.
Read more...
Location
Wimbledon
Duration
36 Weeks
Cost
Negotiated